Creating a Performance-Based Strategy Plan

  1. Choose Start of the navigation path Logistics Next navigation step Plant Maintenance Next navigation step Planned Maintenance Next navigation step Maintenance Planning Next navigation step Maintenance Plans Next navigation step Create Next navigation step Strategy Plan End of the navigation path .

  2. You reach the initial screen for creating a maintenance plan.

  3. Enter the necessary data:

  4. – Enter a maintenance plan category .

    – Enter a performance-based strategy .

    The strategy that you enter must have the scheduling indicator Performance and a dimension other than Time .

  5. Choose .

You reach the initial screen for creating a strategy plan.

  1. Enter the necessary data for the maintenance plan header and the maintenance item and choose .

  2. If you have already created counters for the reference object (for example, equipment) that you have specified in the maintenance item, you reach the dialog box Counter selection .

    Enter the counter whose readings are to serve as a basis for scheduling and choose .

    The counter unit must have the same dimension as the maintenance strategy that you have entered.

  3. Assign a task list to the maintenance item:

  • To assign an existing task list, choose .

  • To create a task list, choose with quick info Create task list / general task list . Assign maintenance packages to the operations of the task list.

After you have assigned a task list, the system displays the following data:

  • The assigned task list on the tab Item

  • The maintenance packages from the strategy assigned to the operations in the task list on the tab Maintenance plan: Cycles

  1. Assign further technical objects to the maintenance item if necessary using the tab Object list (see Object List ).

  1. If you want to create further maintenance items, choose with quick info Create MaintItem.

  • Enter the necessary data, or select an unassigned maintenance item using .

  • Assign a task list if necessary to each of the maintenance items.

  • Assign other technical objects if necessary to the maintenance item.

  • In order to cancel the assignment of a maintenance item to the maintenance plan, choose .

  1. Maintain the scheduling parameters if necessary on the tab Maintenance plan scheduling parameters .

  2. Save the maintenance plan.